Construction Engineering and Management - B.Tech 6th Semester Exam-2023
Construction Engineering and Management
Instructions:
- The marks are indicated in the right-hand margin.
- There are NINE questions in this paper.
- Attempt FIVE questions in all.
- Question No. 1 is compulsory.
- Symbols used (if any) have their usual meanings.
-
An activity is
-
The probabilistic time is given by (Where \( t_o = \) optimistic time, \( t_p = \) pessimistic time and, \( t_n = \) Most likely time)
-
Pert requires
-
Which of the following is a dummy activity?
-
A Gantt chart indicates
-
Negative slack occurs
-
PERT calculation yield a project length of 60 week with a variance of 9 week. Probability factor corresponding to 95% is 1.647; then the number of week required to complete the project with a probability of 95% is
-
Which of the following earth moving machines has the shortest cycle time
-
Which of the following data is not required to prepare an estimate?
-
Force majeure can be
-
(a) Describe various phases of project management.
-
(b) Discuss in brief the basics of slip forming for tall structure.
-
Following table shows details of activities of a small project: (i) Prepare AON network (ii) Prepare AOA network (iii) Identify critical path and duration of project (iv) Work out total, Free and independent floats
Sr. No Activity Preceding Activity Cost per day (Rs. Thousand) Duration 1 A - 5 14 2 B - 6 10 3 C - 4 20 4 D A 8 10 5 E B 4 160 6 F C 3 12 7 G D 3 10 8 H D 5 8 9 I E, F 4 20 10 J G 2 10 11 K H 3 16 12 L I 3 18
-
Explain the application of BIM in project management. What are the safety measures to be considered in the construction site?
-
A target date of completion is to be forecast based on the following information: Item A take 7 weeks for completion; Item B takes 5 weeks; Item C depend on the completion of both A and B, and requires 3 weeks; Item D follow up of item C and requires 2 weeks. Prepare a Gantt chart for scheduling the completion date.
-
(a) Compare and contrast CPM and PERT. Under what circumstance would you use PERT as opposed to CPM in project management?
-
(b) Discuss the objectives of network analysis.
-
(a) What are the factors must be taken into account before selection of construction equipment.
-
(b) calculate the output per day of a concrete mixture of 200 litres. Assume all data reasonably for the purpose.
-
(a) Discuss various rules for providing dummies in a network. What are redundant dummies?
-
(b) What are the methods used for manufacture of precast concrete elements? Explain briefly
-
(a) Explain duties and responsibilities of parties involved in a contract.
-
(b) Differentiate between conventional and mechanized methods of construction.