Construction Engineering and Management - B.Tech 6th Semester Exam., 2022
Construction Engineering and Management
Instructions:
- The marks are indicated in the right-hand margin.
- There are NINE questions in this paper.
- Attempt FIVE questions in all.
- Question No. 1 is compulsory.
- Assume any data not given.
-
For establishing and maintaining priorities among the various jobs of a project, the technique is known as
-
In case of CPM, the performance of a specific task is known as
-
Military organization is also called as
-
Which of the following is incorrect statement?
-
Without affecting the start of succeeding activities, the time by which activity completion time can be delayed, is known as
-
In bar chart, the various activities of a project, are shown by
-
The time which is responsible for least possible construction cost of an activity, is
-
If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively
-
A critical ratio scheduling
-
A machine costs 20,000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be
-
Assess the present constructional infrastructure in India. Give the remedial measures keeping in mind the economic feasibility.
Categorize the different construction works. Explain the different criteria of selection of site for a project.
-
What is critical path method? Prepare the network as per the data given in the Table 1 and compute in a table their early start, early finish, late start and late finish times. Determine the critical path and find the total float and free float for all the activities:
Activity Duration (days) Activity Duration (days) 1-2 8 4-7 0 1-3 10 5-6 4 1-4 5 5-7 3 2-7 6 5-8 6 3-4 3 6-8 5 4-5 7 7-8 5
-
What do you mean by PERT and what is its significance?
As per the given network find the expected time for each of the paths. Also find the critical path as well as the expected time for the project completion.
-
Write the factors to be considered for precast concrete construction. What do you mean by scaffolding?
A project takes 20 days along the critical path and has a standard deviation of 4 days. What is the probability of completing the project within (a) 20 days, (b) 24 days and (c) 18 days?
-
Compare the characteristics and application of the different types of earth excavating equipment. Estimate the output of bulldozer for the following operating conditions: (a) Material - Sandy loam top soil (b) Swell - 25% (c) Haul distance - 45 m (d) Mould board size - 3.0 m long, 1.0 m high (e) Rated mould board capacity - 3 cu.m loose volume (f) Operating factor - 50 min/hr (g) Probable round trip time - 1.87 min.
-
Explain the application of BIM in project management. What are the safety measures to be considered in the construction site?
A target date of completion is to be forecast based on the following information: Item A takes 7 weeks for completion; Item B takes 5 weeks; Item C depends on the completion of both A and B, and requires 3 weeks; Item D follow up of Item C and requires 2 weeks. Prepare a Gantt chart for scheduling the completion date.
-
Explain the importance of organization in construction activities. What are the methods of scheduling?
For the construction of a guesthouse, certain activities are to be performed as shown in Table 2. Activities 2 and 3 can be performed simultaneously and can start only when Activity 1 is completed. Activity 4 can start only after Activity 2 ends. Activity 5 cannot begin until activities 2 and 3 are completed. Activity 6 can start only after Activities 4 and 5 are completed. Activity 7 is the last activity and this can commence only after the completion of Activity 5. (a) Prepare a bar chart for the project. (b) What is the total time taken for the completion of the project?
Activity No. Duration (in weeks) 1 2 2 3 3 5 4 4 5 2 6 3 7 5
-
What is called liquidated damage? What do you mean by direct cost and indirect cost?
The following Table 3 gives the data for the duration and costs of each activity of a project network. The indirect cost of the project is 3,000/week. Determine the optimum duration of project and the corresponding minimum cost. Draw the time scaled version of the network:
Activity Normal Duration (week) Normal Cost (Rs) Crash Duration (week) Crash Cost (Rs) 1-2 6 7,000 3 14,500 1-3 8 4,000 5 8,500 2-3 4 6,000 1 9,000 2-4 5 8,000 3 15,000 3-4 5 5,000 3 11,000